Follo Line Project: Tunnel 2 Completed

Tunnel 2 Completed! On the 15th of July Slab Track team completed the assembly and casting activities on the first tunnel of the EPC TBM Follo Line subproject. With three open fronts, teams will now move in Tunnel 1 working in parallel with Tunnel 4 until its completion before resuming Tunnel 3.

While half of the 40 km of track slab has been performed, finalization works, such as the installation of 120 m permanent rails, are ongoing.

Only thanks to the commitment of the whole team, collaboration with the other departments and Bane NOR this milestone has been achieved.

Looking forward to reaching next ones!